top of page
Bridge Photo 4 Clean.jpg

ROOSEVELT BRIDGE PROJECT

Industry & Partners

Request for Qualifications (RFQ) Issued

Sep. 9, 2025

The Department is issuing a Request for Qualifications (RFQ) to solicit Statements of Qualifications from experienced and qualified firms for replacement of the Roosevelt Memorial Bridge (US-70 over Lake Texoma) joining Marshall and Bryan Counties. This project will be delivered using a Modified Progressive Design-Build (MPDB) approach, which emphasizes early collaboration between the Department and the selected Design-Build teams to optimize project outcomes.

Teams Selected for Roosevelt Bridge Replacement over Lake Texoma

Nov. 3, 2025

The Oklahoma Department of Transportation (ODOT) has selected three design-build teams to work on the US-70 Roosevelt Bridge replacement over Lake Texoma:

 

Manhattan Road & Bridge Company, LLC 

Walsh Construction Company II, LLC

Zachry Construction Corporation / Traylor Bros., Inc. (Joint Venture)

 

ODOT chose these teams based on their experience, team organization, key staff members and their plans for working together and managing project risks. The teams will begin the Accelerated Innovation and Collaboration (AIC) Phase in November 2025. One team will be chosen to perform final design and construction in Spring 2026.

Progressive Design-Build Procurement Update

May 28, 2025

In response to significant storm related damage to the existing U.S. 70 lake causeway sustained on May 19 and 20, the Oklahoma Department of Transportation (ODOT) is accelerating the progressive design-build procurement timeline for the Roosevelt Bridge Project as outlined in the table below. ODOT understands the aggressive nature of this schedule and is working closely with our project partners to prepare for construction later this year.

Sign up for the official solicitation process

Project Timeline

Industry Review Informational Meeting

Aug. 27, 2025

Release Request for Qualifications (RFQ)

September 9, 2025

Release Contract General Provisions & Appendix I (AIC Phase Services)

September 9, 2025

Statements of Qualification (SOQ) due

Sept. 26, 2025

Selection of Teams

Oct. 6, 2025

Begin Accelerated Innovation and Collaboration Phase

Oct. 13, 2025

Alternative Independent Contractor Kick-Off

October 13, 2025

Risk Registers Due from Teams

January 23, 2026

ODOT issues Final Risk Reserve

January 30, 2026

Requests to Continue Due

February 4, 2026

PGMP Due

February 18, 2026

Determination of Which Team Will Receive Design & Construction Task Orders

March 2, 2026

Anticipated Notice to Proceed w/ Design Phase Services

Late March 2026

Industry Review Informational Meeting

August 27, 2025

Completed

Release Request for Qualifications (RFQ)

September 9, 2025

Completed

Release Contract General Provisions & Appendix I (AIC Phase Services)

September 9, 2025

Completed

Statements of Qualification (SOQ) Due

October 13, 2025

Completed

November 3, 2025

Completed

Accelerated Innovations and Collaboration Kick-Off*

November 10, 2025

Completed

Risk Registers Due from Teams

February 20, 2026

Planned

ODOT Issues Final Risk Reserve

February 27, 2026

Planned

Requests to Continue Due

March 4, 2026

Planned

Project Guaranteed Maximum Price Due

March 18, 2026

Planned

Determination of Which Team Will Receive Design & Construction Task Orders

April 2026

Planned

Anticipated Notice to Proceed with Design Phase Services

April 2026

Planned

*Tentative Date

Procure Designer/Builder

Nov. 1, 2023 - April 30, 2024

Completed

Finalize Preferred Alternative

May 1, 2024 - July 23, 2024

Completed

Finalize NEPA

July 24, 2024 - April 1, 2025

Completed

Preliminary Design 

July 24, 2024 - Jan. 1, 2025

Completed

Complete 404

Jan. 22, 2025 - June 10, 2025

In Progress

Review/Approve Builder Estimate

Jan. 22, 2025 - March 25, 2025

In Progress

Final Design

Jan. 22, 2025 - Oct. 28, 2025

In Progress

Right of Way Acquisition

April 2, 2025 - Aug. 4, 2026

Planned

Utility Relocation

Aug. 5, 2026 - April 13, 2027

Planned

Obligate Construction Funding

April 2, 2025 - April 8, 2025

Planned

Release Request for Qualifications (RFQ)

September 9, 2025

Planned

Statements of Qualification (SOQ) due

September 26, 2025

Planned

Selection of Teams

October 6, 2025

Planned

AIC Kick-Off

October 13, 2025

Planned

Requests to Continue Due

February 4, 2026

Planned

Determination of Which Team Will Receive Design & Construction Task Orders

March 2, 2026

Planned

Anticipated Notice to Proceed w/ Design Phase Services

Late March 2026

Planned

Construction

April 9, 2025 - April 4, 2028

Planned

Activity
Proposed Date
Virtual Procurement Kick-off Meeting (Optional)
June 3, 2025
Prime Contractor Team Informational Meeting (Optional)
June 5,6,9, 2025
Release Request for Qualifications (RFQ)
June 16, 2025
Statements of Qualification (SOQ) due
July 2, 2025
Selection of Teams
July 7, 2025
Begin Accelerated Innovation and Collaboration Phase
July 8, 2025
Request to Continue due
September 3, 2025
Determination of Which Team Will Receive Design & Construction Task Orders
September 8, 2025
Anticipated Notice to Proceed
September 15, 2025

Design and construct a high quality, low-maintenance Roosevelt Bridge that will provide generations of reliable service.

Complete the Roosevelt Bridge Project on or before October 1, 2029, and open the new bridge to traffic as soon as practical.

Maximize cost efficiency in all aspects of project delivery.

Engage with the public, local stakeholders, and the engineering and construction industry to make the Roosevelt Bridge Project a model of partnership.

Project Goals

Project Delivery Approach

Superstructure of the old Roosevelt Bridge

A New Way to Build Smarter

ODOT intends to use a method called Modified Progressive Design-Build to deliver the US-70 Roosevelt Bridge Project — the first time this approach has been used by ODOT.​ This delivery model creates a competitive process that encourages innovation and proactive risk management.

With this delivery model, ODOT will work with multiple design and construction teams during an Accelerated Innovation and Collaboration phase. During the AIC phase, teams will compete to develop design concepts for the best bridge, on the best schedule, at the best price. At the end of this phase, a determination will be made on which team will move forward into final design and construction. That team will then work together with ODOT to advance the design and develop a detailed plan to construct the new bridge. This method is a great fit for a project like the US-70 Roosevelt Bridge over Lake Texoma as it promotes a collaborative approach to identify and solve complex challenges.

Distant view of the old Roosevelt Bridge

Why Modified Progressive Design-Build?

  • Encourages competition by engaging multiple teams

  • Incentivizes innovation and collaboration

  • Proactively identifies and allocates risk

  • Establishes project cost-certainty early in the process

Substructure of the old Roosevelt Bridge

Innovative by Design

Modified Progressive Design-Build will help ODOT, and the Design-Build team, proactively identify and manage risk. That means more of the budget goes directly into designing and building the bridge — increasing the project’s overall value. 

 

This method has the ability to shorten the project delivery schedule compared to traditional methods because the Design-Builder typically begins early construction activities before the design is fully complete.

Project Delivery Approach

Progressive Design Build

ODOT intends to deliver the Roosevelt Bridge Project as the state’s first Progressive Design Build (PDB) project. PDB is an alternative delivery procurement method that uses a primarily qualifications-based selection process to select a Design-Builder. Once selected, ODOT and Design-Builder then progress towards an agreed upon design and construction price (thus the term “progressive”). The complexity of the US-70 over Lake Texoma Bridge has many features that will benefit from early owner and contractor collaboration, including the size of the drilled shafts, the depth of the lake, the length of the bridge, and the potential for Accelerated Bridge techniques. PDB delivery allows for:

  • Early selection and involvement of a Design-Builder to ensure that design and construction-related decisions are informed by cost, schedule, risk, and other input from the Design-Builder.
     

  • Project cost and schedule development and refinement during the preconstruction phase.
     

  • Design advancement and risk mitigation which improve cost and schedule accuracy.
     

  • Participation of an independent cost estimator (ICE). The role of the ICE is to develop 
    independent cost estimates for the project that validate the costs submitted by the Design-Builder at pricing milestones.

     

  • Incremental progression of the project over two phases (preconstruction and construction) with an option for ODOT or the Design-Builder to terminate, i.e., “off-ramp”, if the project is not progressing to the mutual satisfaction of the parties.

PDB allows ODOT enhanced ability to minimize unnecessary contingency during the preconstruction phase. If not needed, contingency can create a windfall to the contractor. If the contractor doesn’t estimate contingency correctly, it can cause shortfalls which have a significant negative impact on the overall health of the project and can result in delays and disputes. Use of PDB will improve the return on investment for ODOT because more project funding will go to actual design and construction instead of contingency which may or may not be needed. PDB is anticipated to result in time savings in project delivery, as designer and contractor coordination is initiated early in the process and these entities collaborate with the owner to develop contract requirements. Early constructability input from the contractor can mitigate long lead times and allow for expedited delivery. Permitting is streamlined and the potential for NEPA reevaluation is minimized. Compared to a traditional Design-Bid-Build delivery for the Roosevelt Bridge Project, PDB is anticipated to save ODOT approximately 16 months. This in turn has implications for cost, with savings associated with a reduced period of expenditure.

Bridge Photo 5.jpg

Documents & Reports

Preliminary Engineering Reports

Analysis of Existing Bridge Report

Analysis of Existing Bridge Report

Bryan JP 3387304 U.S. 70 Lake Texoma Alt Selection Letter w attachments

Bryan JP 3387304 U.S. 70 Lake Texoma Alt Selection Letter

Collision Report 2016-2020

Collision Report 2016-2020

Initial Site Assessment Report

Initial Site Assessment Report

Preliminary Engineering Report

Preliminary Engineering Report

Replacement Alignments

Replacement Alignments

Replacement Matrix_Final

Replacement Matrix

Roosevelt Bridge FEMA FIRM Map

Roosevelt Bridge FEMA FIRM Map

Roosevelt Bridge Virtual PI - Website Analytics

Roosevelt Bridge Virtual PI - Website Analytics

Stakeholder Meeting 2021-08-09

Stakeholder Meeting 2021-08-09

Stakeholder Meeting 2023-03-23

Stakeholder Meeting 2023-03-23

Traffic Analysis Memo

Traffic Analysis Memo

Benefit-Cost Analysis

BIP Grant Narrative

BIP Grant Narrative

Traffic & Environmental Studies

Hazmat Report Review

Hazmat Report Review

Waters and Wetlands Report

Waters and Wetlands Report

Events

There are currently no scheduled upcoming events at this time. New events will be added once confirmed.

Past Events

Wednesday, August 27, 2025
Modified Progressive Design-Build Procurement Update

11:00AM

ODOT Headquarters

Commission Meeting Room

200 NE 21st Street, Oklahoma City, OK 73105

Following the industry review period for the Roosevelt Bridge Project, the Oklahoma Department of Transportation (ODOT) is offering a follow-up presentation to all interested proposers. The purpose of this presentation is to provide updates on project status, procurement and the schedule of events. Attendance is encouraged but not required. 


The presentation will be on Wednesday, August 27th, at 11:00 am CDT in the Commission meeting room at ODOT Headquarters, 200 NE 21st Street, Oklahoma City, Oklahoma. A virtual option is available via Zoom using the following link:

Notice of Pending Opportunity

The Department is preparing to issue a solicitation for design and construction services for the Roosevelt Bridge project, which will be delivered using a Modified Progressive Design-Build (MPDB) approach.

Prior to releasing the formal solicitation, we invite prospective design-build teams to review and provide feedback on the draft documents, which can be found on the TOPS Page by clicking the button below.

Tuesday, July 18, 2025
ODOT DBE Outreach Meeting

10:00AM - 12:00 PM
Marshall County OSU Extension Center
Expo Center
11545 Highway 70, Madill, OK 73446


This meeting is for Prime & DBE Design Consultants and Contractors. ODOT and consultant partner HNTB will lead the discussion by describing the Roosevelt Bridge project and the Progressive Design Build process. DBEs should comment on areas in which they believe they can participate, and contractors should comment on areas in which they anticipate using DBE participation.

 

To RSVP, email dbeinfo@odot.org. For questions, contact Jennifer Hankins at (405)708-1846.

Tuesday, June 3, 2025
Virtual Procurement Kick-Off Meeting

During this meeting, the ODOT Project Team will provide updates on the project and an overview of the procurement process and timeline. If you would like to attend, please email Hunter McComack at hmccomack@odot.org and Jason Sanders at jsanders@hntb.com with subject line, “Roosevelt Virtual Procurement Kick-off” requesting a link.

You may also request a date/time for your optional Prime Contractor Team’s informational meeting on the dates listed in this table. Each Prime Contractor Team is offered one 90-minute meeting at ODOT’s District 2 Office located in Antlers.

DRAFT

bottom of page